TIP Narrative & Funding Summary

Executive Summary

Introduction

The Broward Metropolitan Planning Organization (MPO)'s Transportation Improvement Program (TIP) is a five-year program that prioritizes and documents the funding of transportation improvement projects the region expects to build over the next five years. The projects include reconstruction, maintenance, and operation of major highways, arterials, and intersections; maintenance and expansion of the public transit, aviation, and port systems within the Broward region.

The TIP is a tool to advance projects from a Long Range Transportation Plan (LRTP) to a short-range five-year program through the List of Priority Projects (LOPP). All TIP projects are evaluated to ensure consistency with the goals and objectives of the LRTP 2050. The LRTP 2050 is also known as the Commitment 2050 Metropolitan Transportation Plan (2050 MTP).

The Broward MPO is the agency responsible for transportation planning, intergovernmental coordination, and transportation funding allocations in Broward County. Each year, the MPO updates the TIP to decide how to spend federal, state, and local transportation funds for capital projects. Guided by the Broward MPO's goals and objectives, the Broward MPO works with the public, planning organizations, government agencies, elected officials, and community groups to develop the TIP.

Federal Fiscal Years FY 2026-2030 TIP Overview

Investments included in the TIP with funding from the federal (Federal Highway Administration (FHWA), Federal Railroad Administration, and Federal Transit Administration (FTA)), state, and local sources are in excess of $5.1 billion, covering aviation, highways, seaport, rail, and transit. The TIP funds a total of 411 projects.

The funding distribution shows that state funding sources account for about 38% of the TIP. Highway projects worth about $3.5 billion account for nearly 68% of the total funding amount programmed in the five-year period. Of this, $2.7 billion is devoted to the Strategic Intermodal System (SIS) roadways.

Transit Program
About $377 million, making up 7% of the total programmed funding amount to address the capital needs prioritized by Broward County Transit (BCT), South Florida Regional Transportation Authority (SFRTA), and the City of Fort Lauderdale transit agencies. The transit program is predominantly dedicated to maintaining a state of good repair for all assets throughout the transit system and transit operations.
Rail Projects
$993 million, representing about 19% of total investments, to support rail projects for studies, maintenance, operation, and capacity improvements.
Airport Projects
$236 million accounting for 5% of total investments to support facility preservation, capacity improvements, and operations for the four airports: Fort Lauderdale Executive, Fort Lauderdale/Hollywood International Airport, North Perry Airport, and Pompano Beach Airport.
Port Projects
$61 million accounting for 1% of total investments to support the Port Everglades projects for maintaining, operating, and improving its facilities.

The TIP addresses all federally required performance measures and targets, including safety (PM1), bridge and pavement (PM2), system performance (PM3), transit asset management (TAM), and transit safety.

Broward MPO Attributable Funds

During FYs 2026-2030, the Broward MPO plans to fund 49 projects with its attributable funds:

  • 35 pedestrian transportation safety projects worth approximately $81 million
  • 5 major infrastructure projects worth approximately $20 million
  • 8 transportation planning projects worth approximately $48 million
  • 1 transit project worth approximately $1.5 million

Highlights of Projects and Programs

The TIP includes details regarding projects that will be implemented during the next five years. Some highlights include:

Projects

  • $208 million to interchange improvements on the Florida Turnpike at COCONUT CREEK INTERCHANGE
  • $327 million to interchange improvements on SR-9/I-95 from South of SW 10th Street to North of Hillsboro BLVD.
  • $975 million to widen the Sawgrass Expressway from South of NW 8th to East of TPK

Programs

The TIP provides funds for projects in the Broward MPO Roads for Families Program, which includes the Broward MPO Roads for Economic Vitality Program (REV) to improve transportation safety.

Broward MPO Roads for Families Program (RFF)

The TIP funds 42 projects in Broward MPO RFF Program, including REV program, worth approximately $151 million. The focus of the Program is to implement active transportation projects and guide them from the planning phase through design and construction. Projects under this program include transportation safety improvements and other transportation infrastructure that further complement the goals and vision of the 2050 MTP and other initiatives, such as the Congestion Management Process (CMP) / Livability Planning (LP) corridor studies.

Among the 42 projects, 31 are in the Roads for Economic Vitality Program (REV), which is worth about $75 million. The MPO's REV provides funding for small local transportation projects that improve the safety for all transportation users in Broward. This competitive grant program can fund projects such as safety, traffic calming, and intersection improvements, ADA upgrades, and technology advancements such as transit signal priority and traffic control devices.

Public Involvement

The Broward MPO ensures compliance with the public involvement requirements outlined in 23 Code of Federal Regulations 450.316(b) (1) & 450.324(c) and Section 339.175(7), Florida Statutes. Public involvement for the development of the TIP is received through regularly scheduled meetings of the MPO Governing Board and its advisory committees.

Important Dates in the TIP Development Process

March 1, 2024
Submitted the Draft FY 2025 LOPP to FDOT
March 1, 2024
Weekly meeting with FDOT to discuss the FY 2025 LOPP
April 26, 2024
TAC/CAC - Presentation for the FY 2025 LOPP
May 11, 2024
MPO Board - Presentation for the FY 2025 LOPP
May 10, 2024
Submitted the Draft LOPP to the TAC and CAC for review
May 24, 2024
TAC and CAC approved the FY 2025 LOPP
May 25, 2024
Submitted the Draft FY 2025 LOPP to the MPO Board for review
July 11, 2024
MPO Board approved the FY 2025 LOPP
July 11, 2024
Submitted the approved LOPP to District 4
November 7, 2024
Received the Draft Tentative Work Program FY 2026-2030
December 4, 2024
TAC/CAC approved the Draft Tentative Work Program FY 2026-2030
December 12, 2024
MPO Board approved the Draft Tentative Work Program FY 2026-2030
April 16, 2025
FDOT District 4 provided the FY 2026 TIP download files
June 5, 2025
Notice of public meetings and comment period
June 5, 2025
Makes the Draft FY 2026 TIP available for public comment and uploads it on GAP
June 25, 2025
TAC and CAC recommend MPO Board to approve the TIP
July 10, 2025
MPO Board approves TIP FY 2026-2030
July 11 - 15, 2025
Compile public feedback
July 15, 2025
The MPO Submitted the Approved TIP FY 2026-2030

TIP Revision

The TIP may be revised due to changes in project status, project cost, and/or available revenues. These changes can be either a TIP amendment or an administrative modification. Amendment(s) may be for the purpose of deleting projects, adding projects, advancing projects, revising the funding of projects, or modifying the scope or limits of projects. As the MPO Board adopts the amendments, these amendments are incorporated into the Interactive TIP and posted on the BMPO's website at www.BrowardMPO.org under the 'What We Do' tab, select 'Core Products', and select the 'Transportation Improvement Program' tab under 'Amendments.'

An administrative modification is required if changes don't satisfy the TIP amendment criteria. These administrative modifications are approved by the MPO Executive Director and incorporated into the TIP as well.

For comments, send correspondence to:
Broward Metropolitan Planning Organization
100 West Cypress Creek Road
6th Floor, Suite 650
Fort Lauderdale, FL 33309
Contact Us Online
Email: info@browardmpo.org

Legend and Abbreviations

Funding Legend

ACBR
ADVANCE CONSTRUCTION (BRT) - Federal
ACBZ
ADVANCE CONSTRUCTION (BRTZ) - Federal
ACFP
AC FREIGHT PROG (NFP) - Federal
ACID
ADV CONSTRUCTION SAFETY (HSID) - Federal
ACNP
ADVANCE CONSTRUCTION NHPP - Federal
ACNR
AC NAT HWY PERFORM RESURFACING - Federal
ACPR
AC - PROTECT GRANT PGM - Federal
ACSA
ADVANCE CONSTRUCTION (SA) - Federal
ACSS
ADVANCE CONSTRUCTION (SS, HSP) - Federal
ACSU
ADVANCE CONSTRUCTION (SU) - Federal
BNIR
INTRASTATE R/W & BRIDGE BONDS - R/W and Bridge Bonds
BRRP
STATE BRIDGE REPAIR & REHAB - State 100%
CD23
CONGRESS GF EARMARKS HIP 2023 - Federal Earmark
CD24
CONGRESS GF EARMARKS HIP 2024 - Federal Earmark
CIGP
COUNTY INCENTIVE GRANT PROGRAM - State 100%
CM
CONGESTION MITIGATION - AQ - Federal
D
UNRESTRICTED STATE PRIMARY - State 100%
DC
STATE PRIMARY PE CONSULTANTS - State 100%
DDR
DISTRICT DEDICATED REVENUE - State 100%
DEM
ENVIRONMENTAL MITIGATION - State 100%
DI
ST. - S/W INTER/INTRASTATE HWY - State 100%
DIH
STATE IN-HOUSE PRODUCT SUPPORT - State 100%
DIOH
STATE 100% - OVERHEAD - State 100%
DIS
STRATEGIC INTERMODAL SYSTEM - State 100%
DITS
STATEWIDE ITS - STATE 100% - State 100%
DL
LOCAL FUNDS - PTO - BUDGETED - Local
DPTO
STATE - PTO - State 100%
DRA
REST AREAS - STATE 100% - State 100%
DS
STATE PRIMARY HIGHWAYS & PTO - State 100%
DSB2
EVERGLADES PKY/ALLIGATOR ALLEY - Toll/Turnpike
DSBD
I-95 EXPRESS LANES - Toll/Turnpike
DSBF
I-595 - Toll/Turnpike
DSBG
I-75 ML TOLL CAP IMPROVEMENT - Toll/Turnpike
DSPC
SERVICE PATROL CONTRACT - State 100%
FAA
FEDERAL AVIATION ADMIN - Federal
FTA
FEDERAL TRANSIT ADMINISTRATION - Federal
FTAT
FHWA TRANSFER TO FTA (NON-BUD) - Federal Earmark
GFBR
GEN FUND BRIDGE REPAIR/REPLACE - Federal
GFBZ
GENERAL FUND BRIDGE OFF-SYSTEM - Federal
GFNP
NP FEDERAL RELIEF GENERAL FUND - Federal
GFSA
GF STPBG ANY AREA - Federal
GFSU
GF STPBG >200 (URBAN) - Federal
GMR
GROWTH MANAGEMENT FOR SIS - State 100%
HSP
SAFETY (HIWAY SAFETY PROGRAM) - Federal
IM
INTERSTATE MAINTENANCE - Federal
LF
LOCAL FUNDS - Local
NFP
NATIONAL FREIGHT PROGRAM - Federal
NHPP
IM, BRDG REPL, NATNL HWY-MAP21 - Federal
NHTS
NATIONAL HWY TRAFFIC SAFETY - Federal
NSTP
NEW STARTS TRANSIT PROGRAM - State 100%
NSWR
2015 SB2514A-NEW STARTS TRANST - State 100%
PKBD
TURNPIKE MASTER BOND FUND - Toll/Turnpike
PKED
2012 SB1998-TURNPIKE FEEDER RD - State 100%
PKLF
LOCAL SUPPORT FOR TURNPIKE - Local
PKM1
TURNPIKE TOLL MAINTENANCE - Toll/Turnpike
PKYI
TURNPIKE IMPROVEMENT - Toll/Turnpike
PKYO
TURNPIKE TOLL COLLECTION/OPER. - Toll/Turnpike
PKYR
TURNPIKE RENEWAL & REPLACEMENT - Toll/Turnpike
PL
METRO PLAN (85% FA; 15% OTHER) - Federal
PORT
SEAPORTS - State 100%
PROT
PROTECT GRANT PROGRAM - Federal
REPE
REPURPOSED FEDERAL EARMARKS - Federal Earmark
RHH
RAIL HIGHWAY X-INGS - HAZARD - Federal
SA
STP, ANY AREA - Federal
SIB1
STATE INFRASTRUCTURE BANK - SIB
SIWR
2015 SB2514A-STRATEGIC INT SYS - State 100%
SPN
PROCEED FROM SPONSOR AGREEMENT - State 100%
STED
2012 SB1998-STRATEGIC ECON COR - State 100%
SU
STP, URBAN AREAS > 200K - Federal
TALT
TRANSPORTATION ALTS- ANY AREA - Federal
TALU
TRANSPORTATION ALTS- >200K - Federal
TDTF
TRANS DISADV -TRUST FUND - State 100%
TDTF/TDDR
TRANS DISADV -TRUST FUND/DDR USE - State 100%
TM02
EVERGLADES PARKWAY - Toll/Turnpike
TMBD
I-95 EXPRESS LANES - Toll/Turnpike
TMBG
I-75 ML TOLL MAINTENANCE - Toll/Turnpike
TO02
EVERGLADES PARKWAY - Toll/Turnpike
TO10
SAWGRASS EXPRESSWAY - Toll/Turnpike
TOBD
I-95 EXPRESS LANES - Toll/Turnpike
TOBF
I-595 - Toll/Turnpike
TOBG
I-75 ML TOLL OPERATIONS - Toll/Turnpike
TRIP
TRANS REGIONAL INCENTIVE PROGM - State 100%
TRWR
2015 SB2514A-TRAN REG INCT PRG - State 100%

Phase Code Legend

ADM
ADMINISTRATION
CAP
CAPITAL
CST
CONSTRUCTION
DSB
DESIGN BUILD
ENV
ENVIRONMENTAL
FLOAT
Floating Funds
INC
CONTRACT INCENTIVES
MNT
BRDG/RDWY/CONTRACT MAINT
OPS
OPERATIONS
PDE
P D & E
PE
PRELIMINARY ENGINEERING
PLN
PLANNING
ROW
RIGHT OF WAY
RPY
REPAYMENTS
RRU
RAILROAD & UTILITIES

Abbreviations and Definitions

2L, 3L, 4L, 6L, or 8L
2, 3, 4, 6, or 8 Lanes
4 or 6LD
4 or 6 Lanes Divided
ACOE
Army Corps of Engineers
ALOP
Annual Listing of Obligated Projects
ADA
Americans with Disabilities Act of 1990
ATMS
Advanced Traffic Management System
AVE
Avenue
BC
Broward County
BCH
Beach
BCT
Broward County Transit
BCTC
Broward Community Transportation Coordinator
BLVD
Boulevard
BRT
Bus Rapid Transit
CC
County Commission
CEI
Construction Engineering and Inspection
CFR
Code of Federal Regulations
CIP
Capital Improvement Program
CAC
Citizens Advisory Committee
CIRC
Circulation
C/L
County Line
CMAQ
Congestion Mitigation & Air Quality Improvement Program
CMP
Congestion Management Process
CO
County
CRA
Community Redevelopment Authority
CSX RR
Formerly Seaboard Coastline Railroad
CTC
Community Transportation Coordinator
CTD
Commission for the Transportation Disadvantaged
DEO
Department of economic opportunity
DFLTMA
Downtown Fort Lauderdale Transportation Management Association
DOPA
Designated Official Planning Agency
DR
Drive
DRI
Development of Regional Impact
D/W
Districtwide
E
East
EB
Eastbound
ENG
Engineering
E/W
East/West
FAST
Fixing America's Surface Transportation
FAU
Florida Atlantic University
FDOT
Florida Department of Transportation
FEC RR
Florida East Coast Railroad
FHWA
Federal Highway Administration
FIHS
Florida Intrastate Highway System
FLP
Freight, Logistics & Passenger
FM #
Financial Management Number
FMTP
Freight Mobility and Trade Plan
FS
Florida Statues
FTA
Federal Transit Administration
FTPK
Florida's Turnpike
FY
Fiscal Year
HEFT
Homestead Extension of Florida's Turnpike
HOV
High Occupancy Vehicle
HWY
Highway
ICWW
Intracoastal Waterway
IIJA
Infrastructure Investment and Jobs Act
INC
Construction Incentive
ITS
Intelligent Transportation Systems
LCB
Local Coordinating Board
LOS
Level of Service
LRTP
Long Range Transportation Plan
LT
Left Turn
MAP-21
Moving Ahead For Progress in the 21st Century Act
MI
Mile
MP
Mile Post
MPO
Metropolitan Planning Organization
MTP
Metropolitan Transportation Plan
MSC/MISC
Miscellaneous
N
North
N/A
Not Applicable or Not Available
NB
Northbound
NBRT
Northbound Right Turn
NE
Northeast
NEIGH
Neighborhood
NHPP
National Highway Performance Program
NHFP
National Highway Freight Program
NHS
National Highway System
NPMRDS
National Performance Management Research Dataset
NS
North South
NW
Northwest
O & M
Operations & Maintenance
ORT
Open Road Tolling
P3
Public Private Partnership
PH
Phase
PHED
Peak Hour Excessive Delay
PKWY
Parkway
PLN
Planning
PM
Performance Measure
PM1
Safety Performance Measures
PM2
Pavement and Bridge Condition Measures
PM3
System Performance Measures
PTO
Public Transportation Office
PTASP
Public Transportation Agency Safety Plan
RD
Road
REHAB
Rehabilitate
REV
Roads for Economic Vitality
RFF
Roads for Families
RR or R/R
Railroad
RRXING
Railroad Crossing
RSA
Road Safety Audit
RT
Route
R/W
Right-of-Way
S
South

Financial Plan

The TIP is financially constrained for each year, and the federal- and state-funded projects in this document can be implemented using current and proposed revenue sources based on the FDOT Final Tentative Work Program for FY 2026-2030 and locally dedicated transportation revenues. The MPO develops the TIP in cooperation with the State and the transit operators who provide the MPO with estimates of available federal and state funds in order for the MPO to develop its financial plan [23 C.F.R. 450.326(a) and Subsections. 339.175(8), F.S.].

A comprehensive Summary of Funds is displayed in Chapter 4, demonstrating that there are sufficient funds to implement the transportation system improvements [23 C.F.R. 450.326 (k), 23 C.F.R. 450.326 (j), and S. 339. 175 (8)(c)(3) F.S]. Funds are presented in Year of Expenditure (YOE) dollars (adjusted for inflation from the present time to the year of construction for a more accurate cost estimate).

The Broward MPO will continue to pursue opportunities where funds might be added to enhance transportation for all users. Innovative financing resources such as the Public Private Partnership, which is evolving in Florida, are also considered as an alternative funding source to fund and accelerate project delivery.

Project Selection

Projects in the TIP are selected for implementation from the LOPP (List of Priority Projects), in accordance with Title 23 of the United States Code (USC), section 134, as amended by the (IIJA) legislation, and Title 23 of the Code of Federal Regulations, Section 450.332(b).

As a region with a population of over 200,000 individuals, Broward County is part of the Miami Urbanized Area (UZA). This UZA is also known as a Transportation Management Area (TMA). The MPO selects all 23 U.S.C and 49 U.S.C. Chapter 53 funded projects for implementation in consultation with FDOT and public transit operators (except projects on the National Highway System and Tribal Transportation Program).

Tribal Transportation Program, Federal Lands Transportation Program, and Federal Lands Access Program projects are selected by the appropriate federal agencies in cooperation with FDOT and the MPO. Projects within this area that are on the National Highway System are selected by the FDOT in cooperation with the MPO.

The Bridge Program, State Strategic Intermodal System (SIS) and Interstate Maintenance Program are selected for implementation by the State of Florida, in cooperation with the MPO. Additionally, the MPO focuses its prioritization of projects on those that are compatible with the livable communities concept, regionally significant, and those that are part of or connected with the SIS.

Consistency with other Plans

The TIP is consistent with the Broward MPO's Commitment 2050 Metropolitan Transportation Plan (MTP) [23 C.F.R.450.326(n)(1)] and crosses reference projects with corresponding MTP projects by providing MTP ID/Page numbers [s.339.175(8)(c)(7)]. The TIP is also consistent to the maximum extent feasible, with the Seaport Master Plan, the Airport Master Plans, the Broward County Comprehensive Plan, the public transit development plan, and local government comprehensive plans [s. 339.175(8)(a) F.S.].

This consistency is achieved through the LOPP, which is updated annually by the Broward MPO. The LOPP serves as a bridge between the MTP and the TIP, containing the prioritized projects for inclusion in the TIP. The MTP is the primary source for identifying priority projects for inclusion in LOPP.

The MTP provides a coordinated planning effort to mitigate traffic congestion, minimize reconstruction of existing facilities, and allow for adjustment of growth management policies and transportation strategies. The plan is developed in conjunction with the strategic planning factors identified in federal legislation [23 U.S.C. 134(d)]. The MTP identifies improvements in pedestrian, bicycle, transit, roadway, and freight movement networks.

The MTP is coordinated with the State Transportation Plan, Regional Transportation Plan, Broward County Comprehensive Plan, Transit Development Plans, Seaport Master Plan, and Airport Master Plans. In this way, it is the Broward MPO Governing Board that sets project priorities to be programmed by the State into the Work Program and reflected in the TIP.

The MTP guides the expenditure of federal, state, and local transportation funds. Once separate, the urbanized areas in Miami-Dade, Broward, and Palm Beach counties were merged to form the Miami UZA/TMA as reflected in the 2020 U.S. Census. The Miami UZA/TMA extends along the east coast from Miami-Dade County to the southeast corner of Martin County.

In January 2005, the Southeast Florida Transportation Council (SEFTC) was created by the Miami-Dade, Broward, and Palm Beach MPOs to specifically address and coordinate regional transportation issues on behalf of the residents of Southeast Florida. One of SEFTC's primary responsibilities is the development of a Regional Transportation Plan (RTP). An essential element of the RTP is the designation of a Regional Transportation Network. All projects that are on the Regional Transportation Network are eligible for the State Transportation Regional Incentive Program (TRIP) funding.

As required by federal law, the Broward MPO completed its MTP update with a horizon year of 2050 and the Broward MPO Board adopted the 2050 MTP on December 12, 2024. The plan was developed to facilitate travel opportunities in Broward County. The Plan is conceptual in nature and based on travel demand modeling procedures that do not address details of individual projects being considered for implementation.

The 2050 MTP Cost Feasible Plan includes projects and programs for which a reasonable expectation of funding has been identified. The 2050 MTP also includes illustrative projects that have partial funding committed and are expected to be amended into the Cost Feasible Plan once fully funded. An unfunded needs plan included in the 2050 MTP appendix was also created to demonstrate a fuller picture of transportation needs. The unfunded needs plan contains projects that, under current funding conditions, are not financially feasible.

If additional funds become available, the Plan may be amended to include these projects in the cost feasible plan. For additional information on the 2050 MTP and an interactive map of the Cost Feasible Plan, please visit RouteTo2050.org.

Project Priorities

Projects selected for inclusion in the TIP are consistent with federal requirements [23 C.F.R 450.322(b)] and the FDOT Adopted Work Program. These projects are financially feasible for the appropriate funding category and represent the MPO's project priorities. The projects in the List of Priority Projects are evaluated and ranked based upon a screening process that identifies projects that are most important or most significant.

The Broward MPO's LOPP contains projects, in a priority order, that are to be considered for the TIP when funding becomes available. The LOPP is based on the priorities set in the Cost Feasible Plan (CFP) component of the 2050 MTP. The 2050 MTP established the methodology for prioritizing projects in the LOPP.

In order to guarantee transportation investments are balanced among the transportation modes, the MTP established six funding programs, including Technology, Roads for Families, Safety, Highways & Freight, Economic Vitality, and Infrastructure Hardening. Percentages agreed upon in the MTP 2050 by the MPO Board (during the MTP's development) were used to distribute MPO attributable revenue among the six programs.

These percentages are presented in the following Program and Funding Allocation:

Technology
12%
Roads for Families
51%
Safety
10%
Highways & Freight
10%
Economic Vitality
12%
Infrastructure Hardening
5%

Projects within each program were prioritized according to criteria established for each individual program.

Highways & Freight, Roads for Families, Technology, and Economic Development

The prioritization criteria are based on the MTP goals and objectives (adopted by the MPO Board on May 11, 2023) include relevant required Performance Measures identified in the IIJA and were designed for a GIS-based analysis to ensure objectivity in the scoring to the greatest extent practical.

The prioritization process was built on the Commitment 2045 MTP effort and utilized the same six planning factors of mobility, accessibility, safety, demographics, environmental stewardship, and economic vitality. However, for the Route to 2050 MTP, these planning areas were paired to create three planning factors: Mobility and Economic Vitality, Accessibility and Demographics, and Safety and Infrastructure Hardening.

Once all the transportation needs were identified, they were evaluated through the project prioritization process, which scored and ranked transportation projects based on the criteria above. Points were assigned first by dividing a total possible score of 100 by the three factors. Then, the points associated with each factor were adjusted based on the significance of the factor relative to the MTP goals, and to establish a whole number instead of fractions.

This resulted in the weighting of criteria being built into the associated total points available for each factor. Final prioritization scores are a result of the analysis and a total summation of each awarded point per criterion. This prioritization process and scoring approach were endorsed by the Broward MPO Board during its October 12, 2023 meeting.

Roads for Economic Vitality (REV)

REV provides funding for small local transportation projects that will improve safety and mobility for all transportation users. The MPO facilitates an annual competitive grant program to fund projects such as Road for Families projects, traffic calming, and intersection improvements, ADA compliance upgrades, and technology advancements (e.g., transit signal priority and traffic control devices). Projects funded through this program are generally around $4 million each.

REV uses an objective tool to evaluate and rank the application submitted. This tool was developed with direction from the Board and uses several geographic datasets to score the projects. Evaluation criteria weights are 20% for safety, 20% for accessibility, 17% for demographics, 17% for mobility, 13% for economic vitality, and 13% for environmental stewardship.

Infrastructure Hardening

Infrastructure Hardening was a more defined effort to identify the Infrastructure Hardening network throughout the county, for which mitigation and adaptation projects could be identified. The assessment utilized previously completed efforts and data, with some updated data provided by Broward County, and focused on the following:

  • Susceptibility, which was comprised of the following three variables:
    • Sensitivity: The capacity of a facility to handle variations in a climate stressor
    • Exposure: The degree to which a facility is subjected to adverse weather extremes based on impact from the following identified stressors: Coastal Inundation, Flooding, current and future (Precipitation & Storm Surge), Extreme Heat, and Future Groundwater Elevation
    • Adaptive Capacity: The ability of the transportation network to deal with the loss of an impacted facility. This was based on the number of travelers affected and the detour lengths around each affected network segment.
  • Demographics: in recognition of the challenges that socially susceptible populations can face in mobility and recovery, the MPO's Transportation Demographic Areas were incorporated into the assessment.

Susceptibility and demographics were combined (85% susceptible roadways score + 15% demographic score = Infrastructure Hardening Network) to identify the resulting Infrastructure Hardening network. The corridors identified through this effort were used in the prioritization process, and an Infrastructure Hardening funding program was established to address the needs identified.

Safety

Efforts are underway with the development of the Broward Safety Action Plan. Through detailed analysis and public feedback, the plan has identified 11 high-priority corridor locations that require immediate attention. Once project scopes are fully developed, these locations will be incorporated into the MPO's MTP safety program.

Priorities List

The LOPP was presented to the MPO Board last year for consideration and approval. The MPO Board approved the LOPP at their July 11, 2024 meeting.

Implemented Projects – Annual Listing of Obligated Projects (ALOP)

The IIJA [23 C.F.R. 450.334 and s.339.175 (8) (h), F.S.] requires the Broward MPO to publish the ALOP Report and to make it available for public review, on an annual basis, no later than 90 calendar days following the end of the program year.

In responding to the IIJA directive, the FDOT prepared a listing of highway projects, and the MPO, working cooperatively with public transportation providers, developed a listing of transit projects, for which federal funds under 23 U.S.C or 49 U.S.C Chapter 53 were obligated during federal fiscal year 2024 (FFY24) between October 1, 2023 and September 30, 2024.

A public notice for releasing the ALOP Report was published in the South Florida Times. A hard copy of the report is available at the Broward MPO, and an electronic copy of the report is available at the BMPO's website.

Public Involvement and Interagency Consultation

The Broward MPO ensures compliance with the public involvement requirements outlined in 23 Code of Federal Regulations 450.316(b) (1) & 450.324(c) and Section 339.175(7), Florida Statutes.

As part of its ongoing public involvement process, in December 2024, the Broward MPO Board reviewed FDOT's District 4 and Turnpike Enterprise Draft Tentative Work Programs, FY 2026-2030. Comments and concerns were forwarded to FDOT for entry into the records of FDOT's Public Hearing. The Technical Advisory Committee (TAC) and Community Advisory Committee (CAC) also reviewed FDOT's District 4 and the Turnpike Enterprise's Tentative Work Program at their December 2024 meetings.

A 30-day comment period was initiated on June 5, 2025, with a newspaper advertisement in the Sun Sentinel, South Florida Times, and Telemundo. A notice and an electronic copy of the TIP were posted to the Broward MPO website.

As part of the Public Participation Plan, the Broward MPO places a Notice of Public Meeting for the FY 2026-2030 TIP in the eight regional libraries in Broward County. The MPO has also made the TIP document available to the public for review at the Broward MPO office and on the Broward MPO website.

Prior to the adoption of the TIP on July 10, 2025, the Broward MPO also held public meetings during regularly scheduled meetings, providing the public with three opportunities to submit comments. The comment period closed at noon on July 10, 2025.

  • Technical Advisory Committee on Wednesday, June 25, 2025 at 2:30 p.m.
  • Citizens Advisory Committee on Wednesday, June 25, 2025 at 6:00 p.m.
  • Broward MPO Board on Thursday, July 10, 2025 at 9:30 a.m.

The Interactive TIP Tool software is being utilized for TIP development and is a web-based interactive tool. This tool enhances opportunities for the general public to find information and comment on projects in the area through the MPO's website.

The Broward MPO produced a fact sheet explaining the TIP process in both English and Spanish. The fact sheets are available as 7.1 Appendix A of this document, on the MPO's website, in the eight regional libraries, and distributed to our agency's e-mail database.

Certification

The Broward MPO participates in a Federal TMA certification review process with the FHWA and FTA every four years. The MPO's planning process was reviewed at a site visit conducted by the FHWA and FTA on April 11, 2023.

The certification review produced eight noteworthy practices, no corrective actions, and five recommendations. Of these, one recommendation related to the adopted TIP document and process. This recommendation from the Federal Review Team addressed a discrepancy between Federal and State guidance and stressed that all projects added to the TIP must come from the current MTP and cannot be added later to the MTP after a six-month period, as currently allowed under State guidance.

Going forward, with the support of our Federal funding partners, the MPO has committed to reinforcing the Federal guidance on this matter and continuing to work closely with FDOT to ensure planning consistency. Based on the overall findings from the TMA certification review in 2023, the FHWA and FTA jointly certified that the transportation planning process of the entire Miami Urbanized Area TMA, which includes the Broward MPO, substantially meets Federal planning requirements.

The 2023 certification will remain in effect until August 2027. The next TMA certification review will take place in 2027.

The Broward MPO also participates in a State Joint Certification process that is conducted annually by FDOT District Four. The results from the most recent Joint Certification are anticipated to be available in the summer of 2025.

Congestion Management Process (CMP)

The CMP is a structured process for analyzing congestion issues using an objectives-driven, performance-based approach as required in [23 CFR 450.320(a)(b)] Metropolitan Transportation Planning, Final Rule, and [S 339.175(6)(c)(1), F.S.].

The CMP identifies solutions to congestion problems on the state highway system and arterials on the local transportation network. It places emphasis on providing additional transportation alternatives to road capacity improvements wherever possible. As federally required, the CMP continually evaluates the transportation network, identifies congested areas, and recommends operational strategies and capital improvements using the following steps:

  1. Identify the network
  2. Develop regional objectives
  3. Develop multimodal performance measures
  4. Collect data/monitor system performance
  5. Analyze congestion problems and needs
  6. Identify and assess CMP strategies
  7. Program and implement CMP strategies
  8. Evaluate strategy effectiveness

The Broward MPO's CMP includes strategies beyond road widening to manage congestion including safety, versatility, and reducing single occupancy vehicle (SOV) travel. The CMP advances analysis of transportation and land use, leading to recommendations that take a comprehensive approach to implementing the Broward MPO's MTP. The annual development of the MPO's LOPP takes the results and recommendations of the CMP process into consideration as part of the TIP development process.

Transportation Disadvantaged (TD)

Services for people who are transportation disadvantaged, located in Chapter 5.12 of this TIP, are developed pursuant to Subsection 427.015(1) F.S., and Rule 41-2.009(2) of the Florida Administrative Code (F.A.C.).

In Broward County, federal, state, and Broward County government funds will be spent on capital and operating expenses over the next five years to provide both TD and Americans with Disabilities Act (ADA) transportation services. Through these funds, people who qualify for either Florida's TD program or the federal ADA are eligible to receive specialized transportation services.

The Designated Official Planning Agency (DOPA) is the Broward MPO. It coordinates annually with the service provider, Broward County Transit, to update the Transportation Disadvantaged Service Plan.

Broward County Government either purchases, subsidizes, or directly provides special transportation to eligible residents. Broward County, in its role as the Community Transportation Coordinator (CTC) for Broward County, serves the needs of transportation disadvantaged persons. The County Commission has designated the Paratransit Division of the Transportation Department as the responsible agency for administering all contracts for paratransit services and the management of the CTC program. The Director of the Transportation Department is empowered to act for the County Commission in these matters.

The Commission for the Transportation Disadvantaged (CTD) Trust Fund subsidizes a portion of the transportation cost for those who are transportation disadvantaged, for trips that are not sponsored by an agency, and only with a cash or in-kind match. These non-sponsored transportation funds are for "...persons who, because of physical or mental disability, income status, or age, are unable to transport themselves or to purchase transportation…" and include children handicapped or at-risk as defined by FS 411.202.

The County also provides paratransit services in compliance with the Americans with Disabilities Act (ADA) of 1990. ADA/paratransit determination is based on a functional disability that prevents an individual from accessing and/or navigating public transit. The ADA requires the Transportation Department/BCT to offer complementary service to persons with disabilities who are unable to use the fixed-route bus system. The ADA paratransit service offers a level of service comparable to that provided to persons without disabilities who use the fixed-route system.

The LCB provides information, advice, and direction to the CTC on the coordination of TD services and development of service standards that are consistent with the needs and resources of the community.

Federal Discretionary Grants

When an entity in the State of Florida receives a discretionary award through a response to a Notice of Funding Opportunity (NOFO), there are generally three potential project delivery options summarized as follows:

  • Delivery by a local agency as direct recipient: The local agency submits a grant application through Grants.gov and receives an award directly from the federal agency.
  • Delivery through the FDOT Local Agency Program (LAP): The local agency receives an award and FDOT agrees to reimburse the local agency through the FDOT LAP program, the local agency would be a subrecipient to FDOT. This option is only available to FDOT LAP Certified entities. Local agencies must coordinate with FDOT prior to applying to the competitive discretionary grant program.
  • Delivery by FDOT (FDOT Administered): FDOT is the applicant or the local agency requests FDOT to administer the project on their behalf through a local resolution, then FDOT would be the direct recipient.

Projects that are required to be included in the local Transportation Improvement Program (TIP) and Statewide Transportation Improvement Program (STIP)

  • Federal discretionary grants that fund capital projects under Title 23 or Title 49, US Code typically must be in the TIP/STIP before executing a grant agreement with USDOT and/or the appropriate Operating Administration (e.g.: FHWA, FTA, FRA, etc.) or FDOT.
  • If the project is programmed in the FDOT Tentative Five‐year Work Program before July (or earlier if the MPO uses an extract from an FDOT snapshot to build their TIP), then the project will be included in the TIP/STIP that becomes effective October 1.
  • TIP/STIP Amendments are required if the project is not in the current TIP/STIP, and the grant agreement must be executed before October.
  • TIP/STIP Amendments are also required if the project is programmed after July and the grant agreement must be executed before October in the same year.
  • Regionally significant projects that require Federal action by FHWA or FTA, regardless of funding source, must be in the TIP/STIP. Additionally, for information and conformity purposes, the TIP/STIP shall include all regionally significant projects proposed to be funded with Federal funds other than those administered by the FHWA or the FTA, as well as all regionally significant projects to be funded with non‐Federal funds.

When applicable, a TIP/STIP Amendment must be processed using the STIP Amendment application. Consistency with the MPO's TIP and long‐range transportation plan (LRTP) is required to process a STIP Amendment. Additional guidance on STIP Amendments may be found in the Work Program Instructions (Part IV).

Projects that are not required to be included in the TIP/STIP

  • Federal discretionary grants that are not funded under Title 23 (USDOT/FHWA) or Title 49 chapter 53, US Code (Federal Transit Administration), unless it's a regionally significant project.
    • Examples of grants not funded under Title 23 include Safe Streets for All (SS4A) Comprehensive Safety Action Plan Grants.
    • SS4A Implementation Grants may need to be included in the TIP/STIP if they are determined to be regionally significant.
  • Regionally significant projects:
    • Regionally significant projects are transportation projects that are on a facility that serves regional transportation needs (such as access to and from the area outside the region; major activity centers in the region; major planned developments such as new retail malls, sports complexes, or employment centers; or transportation terminals) and would normally be included in the modeling of the metropolitan area's transportation network.
    • At a minimum, this includes projects on all principal arterial highways and all fixed guideway transit facilities that offer an alternative to regional highway travel. Projects that may be grouped in the TIP/STIP or projects exempt from transportation conformity are not considered regionally significant.

Including Federal Discretionary Grant Projects in the FDOT Work Program for TIP/STIP purposes

There are generally three methods that FDOT may consider when including the discretionary project in the FDOT's Tentative Work Program for TIP/STIP purposes or if the Department has agreed to help administer the project.

  • Direct Recipients of Federal Discretionary Funds: Once a direct recipient is notified of the grant award by the Federal agency, i.e. USDOT and/or the appropriate Operating Administration (e.g.: FHWA, FTA, etc.), the local agency should contact the District Work Program Office and District MPO Liaison to discuss steps for programming the project. If the direct recipient administers the project directly with the Federal agency, the FDOT District will only need to program the project for incorporation into the TIP/STIP as a non‐budgeted informational item.
  • Local Agency Delivery through the FDOT LAP Program: If the local agency requests FDOT assistance administering the project or administers the project through the Local Agency Program (LAP), the FDOT District will program the project as budgeted. The local agency would then become a subrecipient to FDOT and the SUBR item group should also be programmed. See the Work Program Instructions (WPI) for additional details if a budgeted project needs to be amended into current year of the adopted work program if the change meets the criteria as provided in Section 339.135(7), F.S. (see WPI, Part III, Chapter 3, Amendments).
  • Delivery by FDOT (FDOT Administered): When FDOT is the applicant or the local agency requests FDOT to administer the project on their behalf through a local resolution, then FDOT would be the direct recipient.

The Broward MPO will collaborate with municipalities, county, and public transit providers to incorporate projects funded by Federal discretionary grants into the TIP through regular TIP updates or necessary TIP amendments.

Projects in FDOT 23 CFR Part 667 Report

The Broward MPO staff has reviewed the FDOT 23 CFR Part 667 Report Periodic Evaluation of Facilities Repeatedly Requiring Repair and Reconstruction Due to Emergency Events.

Roads for Families Initiative

Safety benefits have been directly attributed to roads planned, designed, and operated for all users. To ensure that this is firmly embedded into our transportation planning process, the Broward MPO developed the Roads for Families Initiative. This program, guided by the Roads for Families Advisory Committee (RFAC), ensures that transportation infrastructure is planned and implemented to provide dedicated spaces for all travel modes. The Roads for Families Initiative also serves as a platform to move forward active transportation projects identified in our plans, initiatives, and studies from the planning to design and ultimately to construction.

Because safety is inherent in so many FDOT and Broward MPO programs and projects, and because of the broad and holistic approach FDOT is undertaking with its commitment to Vision Zero, the program of projects in this TIP is anticipated to support progress towards achieving the safety targets.

Pavement and Bridge Condition Measures (PM2)

FHWA's Pavement and Bridge Condition Performance Measures Final Rule, which is also referred to as the PM2 rule, requires state DOTs and MPOs to establish targets for the following six performance measures:

  1. Percent of Interstate pavements in good condition
  2. Percent of Interstate pavements in poor condition
  3. Percent of non-Interstate National Highway System (NHS) pavements in good condition
  4. Percent of non-Interstate NHS pavements in poor condition
  5. Percent of NHS bridges (by deck area) classified as in good condition
  6. Percent of NHS bridges (by deck area) classified as in poor condition

For the pavement measures, five pavement metrics are used to assess condition:

  • International Roughness Index (IRI) - an indicator of roughness (applicable to asphalt, jointed concrete, and continuously reinforced concrete pavements)
  • Cracking percent - percentage of pavement surface exhibiting cracking (applicable to asphalt, jointed concrete, and continuously reinforced concrete pavements)
  • Rutting - the extent of surface depressions (applicable to asphalt pavements only)
  • Faulting - vertical misalignment of pavement joints (applicable to jointed concrete pavements only)
  • Present Serviceability Rating (PSR) – a quality rating applicable only to NHS roads with posted speed limits of less than 40 miles per hour (e.g., toll plazas, border crossings). States may choose to collect and report PSR for applicable segments as an alternative to the other four metrics

Bridge and Pavement Condition Targets

Statewide Targets

Federal rules require state DOTs to establish two-year and four-year targets for the bridge and pavement condition measures. On December 16, 2022, FDOT established 2023 and 2025 statewide bridge and pavement targets, and in September of 2024 adjusted the 2025 target for percent of NHS bridges (by deck area) in poor condition.

Statewide Pavement and Bridge Condition Performance Targets
Performance Measure 2023 Statewide Conditions 2023 Statewide Target 2025 Statewide Target
Percent of Interstate pavements in good condition 67.6% 60.0% 60.0%
Percent of Interstate pavements in poor condition 0.2% 5.0% 5.0%
Percent of non-Interstate NHS pavements in good condition 50.8% 40.0% 40.0%
Percent of non-Interstate NHS pavements in poor condition 0.5% 5.0% 5.0%
Percent of NHS bridges (by deck area) in good condition 55.3% 50.0% 50.0%
Percent of NHS bridges (by deck area) in poor condition 0.6% 10.0% 5.0%

In determining its approach to establishing performance targets for the federal pavement and bridge condition performance measures, FDOT considered many factors:

  • FDOT is mandated by Florida Statute 334.046 to preserve the state's bridges and pavement to specific state-defined standards. To adhere to the statutory guidelines, FDOT prioritizes funding allocations to ensure the current transportation system is adequately preserved and maintained before funding is allocated for capacity improvements. These state statutory guidelines envelope the statewide federal targets that have been established for pavements and bridges.
  • FDOT developed a Transportation Asset Management Plan (TAMP) for the state NHS bridge and pavement assets. The TAMP must include investment strategies leading to a program of projects that would make progress toward achievement of the State's targets for asset condition and performance of the NHS. FDOT's current TAMP was submitted on December 30, 2022 and recertified by FHWA on February 23, 2023.
  • The federal pavement condition measures require a data collection methodology that is a departure from the methods historically used by FDOT. For bridge condition, performance is measured in deck area under the federal measure, while FDOT programs its bridge repair or replacement work on a bridge-by-bridge basis.

FDOT collects and reports bridge and pavement data to FHWA each year to track performance and progress toward the targets. The percentage of Florida's bridges in good condition is slowly decreasing, which is to be expected as the bridge inventory grows older. Reported bridge and pavement data through 2023 exceeded the established targets. FHWA determined that FDOT made significant progress toward its 2023 PM2 targets.

MPO Targets

MPOs must set four-year targets for the six pavement and bridge condition measures within 180 days of FDOT's established targets. MPOs can either agree to program projects in support of the statewide targets or establish their own quantifiable targets for one or more measures in their planning area.

On December 8th, 2022, the Broward MPO agreed to support FDOT's statewide pavement and bridge performance targets and on December 12th, 2024, agreed to support FDOT's adjusted pavement target, thus agreeing to plan and program projects in the TIP that once implemented, are anticipated to make progress toward achieving the statewide targets.

Pavement and Bridge Investments in the TIP

The Broward MPO TIP was developed and is managed in cooperation with FDOT, BCT, and the South Florida Regional Transportation Authority (SFRTA). It reflects the investment priorities established in the 2050 MTP. The TIP includes specific investment priorities that support all of the MPO's goals including maintaining infrastructure, using a prioritization and project selection process established in the MTP.

The TIP devotes a significant amount of projects that will maintain pavement and bridge condition performance. The TIP includes 96 projects that address bridge and pavement conditions. This reflects an overall investment of $83 million for bridges, and $2.2 billion for resurfacing. A subset of those projects is shown below:

  • SR-870/COMMERCIAL BLVD BRIDGE OVER ICWW, BRIDGE REPAIR REHABILITATION FY 2027
  • SR-838/SUNRISE BLVD OVER INTRACOASTAL WATERWAY, BRIDGE REPAIR REHABILITATION FY 2026
  • BRIDGE REPAIR ON DAVIE BLVD BRIDGE OVER SOUTH FORK NEW RIVER, BRIDGE REPLACEMENT, CST FY 2026
  • RESURFACE TPK (SR91) IN BROWARD COUNTY, RESURFACING FY 2026
  • SR-5/US-1/FEDERAL HWY FROM SHERIDAN STREET TO N OF OLD GRIFFIN ROAD, RESURFACING FY 2028

The projects included in the TIP are consistent with FDOT's Five Year Work Program, and therefore to FDOT's approach to prioritize funding to ensure the transportation system is adequately preserved and maintained. Per federal planning requirements, the state selects projects on the NHS in cooperation with the MPO from the approved TIP. Given the significant resources devoted in the TIP to pavement and bridge projects, the MPO anticipates that once implemented, the TIP will contribute to progress towards achieving the statewide pavement and bridge condition performance targets.

System Performance, Freight, & Congestion Mitigation & Air Quality Improvement Program (PM3)

FHWA's System Performance/Freight/CMAQ Performance Measures Final Rule, which is referred to as the PM3 rule, requires state DOTs and MPOs to establish targets for the following six performance measures:

National Highway Performance Program (NHPP)

  1. Percent of person-miles traveled on the Interstate system that are reliable
  2. Percent of person-miles traveled on the non-Interstate NHS that are reliable

National Highway Freight Program (NHFP)

  1. Truck Travel Time Reliability index (TTTR)

Congestion Mitigation and Air Quality Improvement Program (CMAQ)

  1. Annual hours of peak hour excessive delay per capita (PHED)
  2. Percent of non-single occupant vehicle travel (Non-SOV)
  3. Cumulative 2-year and 4-year reduction of on-road mobile source emissions (NOx, VOC, CO, PM10, and PM2.5) for CMAQ funded projects

Because all areas in Florida meet current national air quality standards, the three CMAQ measures do not apply in Florida.

The first two performance measures assess the percent of person-miles traveled on the Interstate or the non-Interstate NHS that are reliable. Reliability is defined as the ratio of longer travel times to a normal travel time over of all applicable roads, across four time periods between the hours of 6 a.m. and 8 p.m. each day.

The third performance measure assesses the reliability of truck travel on the Interstate system. The TTTR assesses the reliability of the Interstate network by comparing trucks' worst travel times against the travel times they typically experience.

System Performance and Freight Targets

Statewide Targets

Federal rules require state DOTs to establish two-year and four-year targets for the system performance and freight targets. On December 16, 2022, FDOT established 2023 and 2025 statewide performance targets, and in September 2024, adjusted the 2025 targets for percent of person miles traveled on the Interstate and on the non-Interstate NHS that are reliable.

Statewide System Performance and Freight Targets
Performance Measure 2023 Statewide Conditions 2023 Statewide Target 2025 Statewide Target
Percent of person-miles on the Interstate system that are reliable 82.8% 75.0% 75.0%
Percent of person-miles on the non-Interstate NHS that are reliable 89.1% 50.0% 60.0%
Truck travel time reliability (Interstate) 1.48 1.75 2.00

FDOT collects and reports reliability data to FHWA annually to track performance and progress toward the reliability targets. Actual performance in 2023 was better than the 2023 targets. System performance and freight are addressed through several statewide initiatives:

  • Florida's Strategic Intermodal System (SIS) is composed of transportation facilities of statewide and interregional significance. The SIS is a primary focus of FDOT's capacity investments and is Florida's primary network for ensuring a strong link between transportation and economic competitiveness. These facilities, which span all modes and includes highways, are the workhorses of Florida's transportation system and account for a dominant share of the people and freight movement to, from and within Florida. The SIS includes 92 percent of NHS lane miles in the state. Thus, FDOT's focus on improving performance of the SIS goes hand-in-hand with improving the NHS, which is the focus of the FHWA's TPM program. The SIS Policy Plan was updated in early 2022 consistent with the updated FTP. The SIS Policy Plan defines the policy framework for designating which facilities are part of the SIS, as well as how SIS investments needs are identified and prioritized. The development of the SIS Five-Year Plan by FDOT considers scores on a range of measures including mobility, safety, preservation, and economic competitiveness as part of FDOT's Strategic Investment Tool (SIT).
  • Freight Mobility and Trade Plan (FMTP) defines policies and investments that will enhance Florida's economic development efforts into the future. The FMTP identifies truck bottlenecks and other freight investment needs and defines the process for setting priorities among these needs to receive funding from the National Highway Freight Program (NHFP). Project evaluation criteria tie back to the FMTP objectives to ensure high priority projects support the statewide freight vision. In May 2020, FHWA approved the FMTP as FDOT's State Freight Plan. An update to the FMTP will be adopted in the spring of 2025.

MPO Targets

MPOs must establish four-year targets for all three performance measures. They can either agree to program projects that will support the statewide targets or establish their own quantifiable targets for one or more measures for their planning area.

On December 8th, 2022, the Broward MPO agreed to support FDOT's statewide system performance and freight targets and on December 12th, 2024 agreed to support FDOT's adjusted 2025 reliability targets, thus agreeing to plan and program projects in the TIP that once implemented, are anticipated to make progress toward achieving the statewide targets.

System Performance and Freight Investments in the TIP

The Broward MPO TIP was developed and is managed in cooperation with FDOT and transit providers: BCT and the SFRTA. It reflects the investment priorities established in the 2050 MTP. The TIP includes specific investment priorities that support all of the MPO's goals including reducing travel time and Achieving Level of Service (LOS) standards, using a prioritization and project selection process established in the MTP.

The TIP devotes a significant amount of resources to programs and projects that will improve system performance and freight reliability on the Interstate and non-Interstate NHS. The Broward MPO TIP will fund:

  • $75 million for intersection improvement
  • $2.7 billion for congestion relief projects
  • $2.3 billion for freight
  • $20 million for TDM projects
  • $1.8 billion for managed lanes
  • $1.0 billion for TSM&O projects

A subset of those projects is shown below:

  • SR-820/PINES BOULEVARD @ FLAMINGO ROAD, INTERSECTION IMPROVEMENTS PDE FY 2024/25/26, PE FY2027/28
  • SR-817/UNIVERSITY DRIVE FROM NOVA DRIVE TO SR-84, TRAFFIC OPS IMPROVEMENT, CST FY 2026
  • WIDEN SAWGRASS (SR 869) UNIVERSITY DR TO SR7 (MP 14.8-18.4)(6TO10 LNS), ADD LANES & RECONSTRUCT, CST FY 2027
  • SR-9/I-95 FROM SOUTH OF SW 10TH STREET TO NORTH OF HILLSBORO BLVD. ,DSB FY 2026/2027
  • SR-9/I-95 @ FROM N OF COMMERCIAL BLVD. TO N OF CYPRESS CREEK ROAD INTERCHANGE - ADD LANES, FY 2029/2030

The projects included in the TIP are consistent with FDOT's Five Year Work Program, and therefore to FDOT's approach to prioritize funding to address performance goals and targets. Per federal planning requirements, the state selects projects on the NHS in cooperation with the MPO from the approved TIP. Given the significant resources devoted in the TIP to programs that address system performance and freight, the MPO anticipates that once implemented, the TIP will contribute to progress towards achieving the statewide reliability performance targets.

Transit Asset Management Measures

FTA's Transit Asset Management (TAM) regulations apply to all recipients and subrecipients of Federal transit funding that own, operate, or manage public transportation capital assets. The regulations define the term "state of good repair," require that public transportation providers develop and implement TAM plans, and established state of good repair standards and performance measures for four asset categories: equipment, rolling stock, transit infrastructure, and facilities.

FTA TAM Performance Measures
Asset Category Performance Measure
Equipment Percentage of non-revenue, support-service and maintenance vehicles that have met or exceeded their useful life benchmark
Rolling Stock Percentage of revenue vehicles within a particular asset class that have either met or exceeded their useful life benchmark
Infrastructure Percentage of track segments with performance restrictions
Facilities Percentage of facilities within an asset class rated below condition 3 on the TERM scale

For equipment and rolling stock classes, Useful Life Benchmark (ULB) is defined as the expected lifecycle of a capital asset, or the acceptable period of use in service, for a particular transit provider's operating environment. ULB considers a provider's unique operating environment such as geography, service frequency, etc.

Public transportation agencies are required to establish and report transit asset management targets annually for the following fiscal year. Each public transit provider or its sponsors must share its targets with each MPO in which the transit provider's projects and services are programmed in the MPO's TIP. MPOs are not required to establish TAM targets annually each time the transit provider establishes targets. Instead, MPO targets must be established when the MPO updates the LRTP (although it is recommended that MPOs reflect the most current transit provider targets in the TIP if they have not yet taken action to update MPO targets).

The TAM rule defines two tiers of public transportation providers based on size parameters:

  • Tier I providers are those that operate rail service or more than 100 vehicles in all fixed route modes, or more than 100 vehicles or more in one non-fixed route mode
  • Tier II providers are those that are a subrecipient of FTA 5311 funds, or an American Indian Tribe, or have 100 or less vehicles across all fixed route modes, or have 100 or less vehicles in one non-fixed route mode

A Tier I provider must establish its own transit asset management targets, as well as report performance and other data to FTA. A Tier II provider can establish its own targets or participate in a Group Plan with other Tier II providers whereby targets are established for the entire group in coordination with a group plan sponsor, typically a state DOT.

Transit Asset Management Targets

The Broward MPO planning area is served by two Tier 1 transit providers: BCT and SFRTA and therefore must develop TAM Plans. BCT's TAM Plan includes the following Tier 2 transit providers: Coconut Creek, Coral Springs, Dania Beach, Davie, Deerfield Beach, Fort Lauderdale, Hallandale Beach, Hillsboro Beach, Hollywood, Lauderdale-by-the-Sea, Lauderdale Lakes, Lauderhill, Lighthouse Point, Margate, Miramar, Pembroke Pines, Pompano Beach, Tamarac, and West Park.

On December 12th, 2024, the Broward MPO established transit asset targets for the MPO planning area. These targets were established in consultation with and reflect the targets established by BCT and SFRTA through their TAM Plans. The targets for rolling stock, particularly buses and vans, reflect a composite of all the transit agencies' targets. In instances where targets applied to one specific agency, such as locomotives and track restrictions, the MPO adopted that agency's target.

The Broward MPO TAM Targets
Asset Category - Performance Measure Asset Class/Type FY 2024 Asset Condition 2025 Target
Rolling Stock - Percentage of revenue vehicles that have met or exceeded their Useful Life Benchmark (ULB) Cutaway Bus (CU) 0% 0%
Paratransit Mini Van (MV) 0% 0%
40 Foot Bus (BU) 0% 0%
60 Foot Bus Articulated Bus (AB) 0% 0%
45 Foot Bus (BR) 0% 0%
Commuter Rail Locomotive (RL) 30% 30%
Commuter Rail Passenger Coach (RP) 30% 30%
Commuter Rail self-propelled passenger car (RS) 30% 30%
Equipment - Percentage of non-revenue, support-service and maintenance vehicles that have met or exceeded their Useful Life Benchmark (ULB) All non-revenue vehicles 35% 50%
Other rubber tire vehicles 23.5% 0%
Facilities - Percentage of facilities rated below Condition 3.0 on the FTA Transit Economic Requirements Model (TERM) Passenger, maintenance, parking and administrative facilities 16.5% 5%
Infrastructure - Percentage of track segments with performance restrictions Rail fixed guideway, track and signals 0.2% 4%

Transit Asset Management Investments in the TIP

The Broward MPO TIP was developed and is managed in cooperation with BCT and SFRTA. It reflects the investment priorities established in the 2050 MTP and BCT and SFRTA's TAM Plans.

Transit asset condition and state of good repair is a consideration in the methodology Broward MPO and the transit agencies use to select projects for inclusion in the TIP. The Broward MPO TIP, once implemented, will make progress toward achieving these targets.

Chapters 5.3, 5.4 and 5.5 of the Broward MPO's TIP documents all funds (local, FTA and STP) that will be used by BCT and SFRTA to improve the condition of the region's transit assets. The Broward MPO TIP includes 33 projects that address transit state of good repair. This reflects an overall investment of $1.0 billion. A subset of those projects is shown below:

  • Broward County Transit Section 5339 Bus and Bus facilities
  • SFRTA Section 5337 State of Good Repair
  • SFRTA Capital Section 5339 Bus and Bus Facilities

The TIP includes specific investment priorities that support all of the MPO's goals, including transit state of good repair, using a prioritization and project selection process established in the LRTP. This process evaluates projects that, once implemented, are anticipated to improve transit state of good repair in the MPO's planning area. The MPO's goal of improving transit asset condition is linked to this investment plan, and the process used to prioritize the projects within the TIP is consistent with federal requirements.

The Broward MPO TIP has been evaluated and the anticipated effect of the overall program is that, once implemented, progress will be made towards achieving the transit asset performance targets. The Broward MPO will continue to coordinate with the BCT and SFRTA to maintain the region's transit assets in a state of good repair.

Transit Safety Performance

FTA's Public Transportation Agency Safety Plan (PTASP) regulations established transit safety performance management requirements for providers of public transportation systems that receive federal financial assistance under 49 U.S.C. Chapter 53.

The regulations apply to all operators of public transportation that are a recipient or sub-recipient of FTA Urbanized Area Formula Grant Program funds under 49 U.S.C. Section 5307, or that operate a rail transit system that is subject to FTA's State Safety Oversight Program. The PTASP regulations do not apply to certain modes of transit service that are subject to the safety jurisdiction of another Federal agency, including passenger ferry operations regulated by the United States Coast Guard, and commuter rail operations that are regulated by the Federal Railroad Administration.

The PTASP must include performance targets for the performance measures established by FTA in the National Public Transportation Safety Plan, which was published on January 28, 2017. The transit safety performance measures are:

  • Total number of reportable fatalities and rate per total vehicle revenue miles by mode
  • Total number of reportable injuries and rate per total vehicle revenue miles by mode
  • Total number of reportable safety events and rate per total vehicle revenue miles by mode
  • System reliability – mean distance between major mechanical failures by mode

Each Section 5307 or 5311 public transportation provider in Florida must develop a System Safety Program Plan (SSPP) under Chapter 14-90, Florida Administrative Code. FDOT technical guidance recommends that Florida's transit agencies revise their existing SSPPs to be compliant with the FTA PTASP requirements.

Each provider of public transportation that is subject to the PTASP regulations must certify that its SSPP meets the requirements for a PTASP, including transit safety targets for the federally required measures. Providers were required to certify their initial PTASP and safety targets by July 20, 2021. Once the public transportation provider establishes safety targets it must make the targets available to MPOs to aid in the planning process. MPOs are not required to establish

5-Year Summary of Projects by Funding Category

DPTO - State PTO Projects

The State Public Transportation Office (DPTO) funding category includes airport improvements, rail crossing projects, and water transportation initiatives totaling $96,045,658 over the five-year period.

Major airport improvement projects include:

  • Fort Lauderdale Executive Airport Western Extension & Parallel Taxiway - $2,275,380 total
  • North Perry Airport Runway 1R-19L & Taxiway E Lighting Improvements - $2,640,000 in FY 2029
  • Pompano Beach Airpark Wildlife Hazard Mitigation Construction - $1,200,000 in FY 2028

Rail infrastructure projects include the Florida East Coast Railway improvements from Miami-Dade/Broward line to Palm Beach/Martin County line at $4,500,000 in FY 2026, and various South Florida Rail Corridor projects including grade crossing rehabilitations and monitoring systems.

Annual funding distribution shows the highest investment in FY 2026 at $38,170,992, followed by $18,820,325 in FY 2027.

DS - State Primary Highways & PTO

State primary highway projects total $39,777,493 and focus on traffic operations, safety improvements, and highway infrastructure maintenance.

Key ongoing programs include:

  • Continuing Services for TMS&O ITS Services - $300,000 annually
  • I-95/75 Severe Incident Response Vehicle (SIRV) - $4,431,566 in FY 2029-2030
  • Continuing Services for Safety Studies and Road Safety Audits - $2,150,000

Major construction projects include SR-9/I-95 improvements from south of SW 10th Street to north of Hillsboro Boulevard at $7,315,220 in FY 2027 and SR-817/University Drive improvements totaling $3,400,000 in FY 2026.

DSB2 - Everglades Parkway/Alligator Alley

Alligator Alley improvements total $32,124,765 with major construction occurring in FY 2028 at $22,478,924.

Projects include SR-93/I-75 improvements between mile markers 18.075-45.361, master planning for Broward County, boat ramp facilities, and guardrail installations for safety enhancements.

DSBD - I-95 Express Lanes

I-95 Express Lanes funding totals $122,700,196, representing the largest ongoing financial commitment in the TIP.

The primary component is service contract payments per Section 339.0809, Florida Statutes, with annual payments ranging from $15,931,951 in FY 2026 to $34,071,537 in FY 2030. Additional funding of $1,856,567 supports Broward Boulevard truck parking expansion at the I-95 interchange.

DSBF - I-595

The I-595/SR-862 Public-Private Partnership project from east of I-75 to west of I-95 includes $5,481,000 in funding for FY 2029-2030.

DSBG - I-75 ML Toll Cap Improvement

SR-9/I-95 improvements at SR-842/Broward Boulevard total $4,301,000, with $3,093,150 programmed in FY 2026 and $1,207,850 in FY 2030.

DSPC - Service Patrol Contract

The Broward County Road Ranger Service Patrol program totals $22,389,585 over the five-year period, providing incident management and motorist assistance services along major corridors.

FAA - Federal Aviation Administration

Federal aviation funding totals $51,605,780 for airport infrastructure improvements across Broward County's general aviation airports.

Major projects include:

  • Fort Lauderdale Executive Airport taxiway extensions - $7,017,840
  • Fort Lauderdale-Hollywood International Airport Taxilane T rehabilitation - $14,141,250
  • Fort Lauderdale Executive Airport Taxiways L&P extension - $6,607,440 in FY 2028
  • North Perry Airport ATC Tower replacement - $5,606,550
  • Pompano Beach Airpark runway rehabilitations - $6,364,000

FTA - Federal Transit Administration

Federal transit funding represents the largest category at $574,215,020, supporting both formula grants and the Broward Commuter Rail project.

Section 5307 Formula Grants - Broward County
$147,600,000 for large urban area capital investments
Section 5307 Formula Grants - SFRTA
$122,268,228 for South Florida Regional Transportation Authority
Section 5337 Formula Grants - SFRTA
$136,120,792 for fixed guideway improvements
Broward Commuter Rail (BCR) South
$148,500,000 for new rail service development

FTAT - FHWA Transfer to FTA

Highway funds transferred to transit projects total $3,794,540 in FY 2026 for South Florida Rail Corridor railroad crossing improvements.

GFBR - General Fund Bridge Repair/Replace

Bridge repair and replacement projects on West Lake Drive total $8,793,667 in FY 2027, addressing three river crossings:

  • Lucille River Bridge - $4,365,209
  • Mercedes River Bridge - $1,532,264
  • Estelle River Bridge - $2,896,194

GFBZ - General Fund Bridge Off-System

Off-system bridge improvements total $6,349,412 in FY 2027, including West Lake Drive river crossings and SE 7th Street at Rio Cordova Bridge.

GMR - Growth Management for SIS

Strategic Intermodal System (SIS) growth management projects total $259,235,305, supporting major infrastructure investments.

Key projects include:

  • I-595/SR-862 Public-Private Partnership - $190,088,937
  • Fort Lauderdale-Hollywood International Airport Automated People Mover - $44,325,000
  • Port Everglades bulkhead improvements - $20,406,214

LF - Local Funds

Local funding contributions total $293,563,619, demonstrating significant local investment in transportation infrastructure.

Major local investments include:

  • Broward Commuter Rail (BCR) South local match - $74,250,000
  • Fort Lauderdale-Hollywood International Airport Automated People Mover - $68,393,279
  • Broward County Block Grant Operating Assistance - $61,547,673
  • Port Everglades infrastructure improvements - $5,700,000

Annual local contributions are highest in FY 2026 at $88,405,138, reflecting the front-loaded nature of several major projects.

NSTP - New Starts Transit Program

Federal New Starts funding for the Broward Commuter Rail (BCR) South project totals $44,203,600 over FY 2026-2028.

NSWR - 2015 SB2514A New Starts Transit

Additional state new starts transit funding for Broward Commuter Rail totals $30,046,400 over FY 2026-2028.

PKBD - Turnpike Master Bond Fund

Florida Turnpike bond funding totals $965,952,308, representing the largest single funding category for major highway capacity expansion.

Major Sawgrass Expressway (SR-869) widening projects include:

  • Sunrise Boulevard to Oakland Park Boulevard - $352,379,078
  • Oakland Park Boulevard to Atlantic Boulevard - $165,509,293
  • Sample Road to University Drive - $133,906,766
  • South of NW 8th Street to Sunrise Boulevard - $130,548,148
  • Coconut Creek Interchange modifications - $180,013,023

FY 2026 represents the peak investment year at $426,114,207, followed by $345,014,078 in FY 2027.

PKLF - Local Support for Turnpike

Local contributions to Turnpike projects total $40,694,472, including $20,000,000 for Sawgrass Expressway improvements and $19,583,600 for Coconut Creek Interchange modifications.

PKM1 - Turnpike Toll Maintenance

Ongoing Turnpike maintenance totals $2,462,606, including I-595 Public-Private Partnership maintenance and Sawgrass Expressway highway lighting at $220,000 annually.

PKYI - Turnpike Improvement

Turnpike improvement projects total $336,999,711, focusing on capacity expansion and operational enhancements.

Major projects include:

  • Sawgrass Expressway University Drive to SR-7 widening - $161,835,157
  • Turnpike widening projects at multiple locations - $127,172,378
  • Griffin Road Interchange improvements - $14,603,756

PKYO - Turnpike Toll Collection/Operations

Sawgrass Expressway toll operations require $5,050,000 annually, totaling $25,250,000 over the five-year period.

PKYR - Turnpike Renewal & Replacement

Turnpike renewal and replacement projects total $22,128,071 in FY 2026, including mainline resurfacing and safety improvements in Broward County.

PL - Metro Plan (85% FA; 15% Other)

Metropolitan planning activities through the Unified Planning Work Program (UPWP) total $19,124,087 over the five-year period, supporting ongoing transportation planning activities.

PORT - Seaports

Port Everglades upland facility improvements total $3,200,000 in FY 2026.

SA - STP, Any Area

Surface Transportation Program funding for any area totals $19,071,729, supporting various highway improvement projects throughout Broward County.

Major projects include SR-824/Pembroke Road improvements at $3,874,279 in FY 2029 and various arterial road improvements along US-27, I-75, and other state roads.

SU - STP, Urban Areas > 200K

Surface Transportation Program funding for large urban areas totals $60,162,029 (partial data shown), supporting local street improvements, planning activities, and urban arterial projects.

Significant investments include Pembroke Road improvements from Douglas Road to University Drive at $13,627,777 and various municipal transportation projects throughout Broward County's urban areas.